Aurum Exploration Services work on their first gypsum project in Angola

Aurum Exploration Services work on their first gypsum project in AngolaAurum Exploration Services work on their first gypsum project in Angola

Data

Project Date: 2010 - 2013

Project Location: Angola

Project Duration: Ongoing

Services Used: GIS Services, Data & Map Compilations, Target Generation, Core Logging, QAQC of laboratory samples and Resource Estimation

Snapshot

– A consortium of three major companies chose Aurum to lead an exploration project for quality gypsum in Angola
– A team of three geologists undertook the exploration and drilling programme in the target areas
– The project is on-going, pending results of the most recent drill core analyses, however initial results are positive

PROJECT BRIEF

A consortium of three major companies – two local Angolan partners and a German firm – are investigating the gypsum potential of the country with the aim of identifying a 5 million tonne resource of suitable quality gypsum to supply the nation’s first indigenous plasterboard manufacturing plant.

The group chose Aurum Exploration Services to lead the exploration project as Aurum have been operating in Angola since 2005. The positive reputation acquired during that period resulted in Aurum being recommended to the consortium by Micon International Limited.

Senior geologist Graham Parkin led the Aurum team working in Angola to complete the project.

CHALLENGES

The project was an exciting new challenge for Aurum as this was the first time the organisation has worked on a major gypsum resource.
The team of Aurum geologists faced several challenges during this project:

  • The preferred quality of gypsum for plasterboard is > 85% purity with strict limitations on certain other impurities/undesirables, therefore finding a suitable deposit is challenging in itself
  • Understanding the particular parameters of gypsum quality for various end uses and the economics of a gypsum deposit
  • Due to concerns over impurities and dimensions of the initial target, a secondary target had to be identified
  • Locating a laboratory which could carry out the appropriate analyses at a cost effective rate
  • Based on results from limited drilling and geological mapping a drill programme had to be designed and completed to provide adequate data to define an initial resource

SOLUTION

The team, made up of three Aurum geologists began the on-site exploration process. They were supported in country by the client and with technical support and guidance by the project manager and technical staff in the Aurum office in Ireland. Outside expertise was sought from recognised gypsum experts where necessary.

Resource Development

  • The primary target area was found to be unviable, so the Aurum team identified new targets using our knowledge of the economic geology of Angola and created a grass roots prospecting and mapping plan
  • The team identified a target close to an existing area previously mapped by Aurum
  • Aurum geologists mapped and prospected the target. Gypsum was identified at surface over a wide area and a test hole was drilled, yielding positive results.
  • A further phased drilling programme was designed in order to determine whether the amount of suitable quality gypsum was likely to represent a 5 million tonne resource
  • Drill core was sampled according to industry best practice and in a manner designed to minimise costs to the consortium, preserve geological integrity and generate the best possible dataset to interpret
  • Based on positive results from the initial programme, a further drilling programme has been completed from which a resource model will be developed in 2013

RESULTS

This project is on-going, pending on results of the drill core analysis from the most recent phase of drilling and a resource estimation will be prepared for the client in Q3 2013.